[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142674":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1142674,799,1,"单选题","工程项目施工组织设计中，一般将施工顺序的安排写入()（2013）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工进度计划",false,{"key":16,"text":17,"correct":14},"B","施工总平面图",{"key":19,"text":20,"correct":21},"C","施工部署和施工方案",true,{"key":23,"text":24,"correct":14},"D","工程概况","施工部署及施工方案 包括( 1 ) 根据工程情况，结合人力、材料、机械设备、资金、施工方法等条件，全面部署 施工任务，合理安排施工顺序，确定主要工程的施工方案； ( 2 ) 对拟建工程可能采用的几个施工方案进行定性、定量的分析，通过技术经济评 价 ，选择最佳方案。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]