[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142666":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142666,799,1,"单选题","根据项目目标动态控制的工作程序，第一步工作是()（2013）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进行项目目标分解",true,{"key":16,"text":17,"correct":18},"B","收集项目目标的实际值",false,{"key":20,"text":21,"correct":18},"C","进行目标的计划值与实际值比较",{"key":23,"text":24,"correct":18},"D","确定各种资源投入量","",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]