[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142663":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1142663,799,1,"单选题","某项目专业性强且技术复杂，开工后，由于专业原因该项目的项目经理不能胜任该项目，为了保证项目目标的实现，企业更换了项目经理。企业的此项行为属于项目目标动态控制的()（2013）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","管理措施",false,{"key":16,"text":17,"correct":14},"B","经济措施",{"key":19,"text":20,"correct":14},"C","技术措施",{"key":22,"text":23,"correct":24},"D","组织措施",true,"组织措施，例如调整项目组织结构、任务分工、管理职能分工、工作流程组织和项目管理班子人员等。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]