[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142660":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142660,799,2,"多选题","编制施工组织总设计时，必须遵循的顺序有( )。（2012）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","确定施工部署后，才能制定施工方案",true,{"key":16,"text":17,"correct":18},"B","撰写施工方案后，才能编制进度计划",false,{"key":20,"text":21,"correct":18},"C","计算完工程量后，才能确定施工部署",{"key":23,"text":24,"correct":18},"D","确定资源需求量计划后，才能编制施工准备工作计划",{"key":26,"text":27,"correct":14},"E","编制进度计划后，才能编制资源需求量计划","AE","@##",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]