[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142657":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142657,799,1,"单选题","根据《建筑施工组织设计规范》GB\u002FT50502-2009，“合理安排施工顺序”属于施工组织设计中（ ）的内容。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工部署和施工方案",true,{"key":16,"text":17,"correct":18},"B","施工进度计划",false,{"key":20,"text":21,"correct":18},"C","施工平面图",{"key":23,"text":24,"correct":18},"D","施工准备工作计划","本题考查的是施工组织设计的基本内容。施工部署及施工方案包括：根据工程情况，结合人力、材料、机械设备、资金、施工方法等条件，全面部署施工任务，合理安排施工顺序，确定主要工程的施工方案。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]