[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142656":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142656,799,2,"多选题","项目施工过程中，对施工组织设计进行修改或补充的情形有（ ）。2017",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","设计单位应业主要求对楼梯部分进行局部修改",false,{"key":16,"text":17,"correct":18},"B","某桥梁工程由于新规范的实施而需要重新调整施工工艺",true,{"key":20,"text":21,"correct":18},"C","由于自然灾害导致施工资源的配置有重大变更",{"key":23,"text":24,"correct":18},"D","施工单位发现设计图纸存在重大错误需要修改工程设计",{"key":26,"text":27,"correct":14},"E","某钢结构工程施工期间，钢材价格上涨","BCD","本题考查的是施工组织设计的动态管理。项目施工过程中，发生以下情况之一时，施工组织设计应及时进行修改或补充：（1）工程设计有重大修改；（2）有关法律、法规、规范和标准实施、修订和废止；（3）主要施工方法有重大调整；（4）主要施工资源配置有重大调整；（5）施工环境有重大改变。选项A，局部修改，不需要进行施工组织设计的修改或补充。选项E，钢材价格上涨不需要进行施工组织设计的修改或补充。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]