[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142630":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142630,799,2,"多选题","关于施工总承包管理模式特点的说法，正确的有( )。（2013）",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","业主方的招标及合同管理工作量较大",true,{"key":16,"text":17,"correct":14},"B","分包工程任务符合质量控制的“他人控制”原则，对质量控制有利",{"key":19,"text":20,"correct":14},"C","各分包工程之间的关系由施工总承包管理单位负责协调，这样可以减轻业主方的管理的工作量",{"key":22,"text":23,"correct":24},"D","在开工前有较明确的合同价，有利于业主的总投资控制",false,{"key":26,"text":27,"correct":24},"E","多数情况下，由业主方与分包人直接签约，这样有可能减少业主方的风险","ABC","D选项的正确说法应该是在进行对施工总承包管理单位的招标时，只确定施工总承包管理费，而不确定工程总造价，这可能称为业主控制总投资的风险，E选项的正确说法是多数情况下，由业主方与分包人直接签约，这样有可能增加业主的风险。 -45。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]