[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142629":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142629,799,1,"单选题","根据物资采购管理程序，物资采购首先应（）。 （2014）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进行采购策划，编制采购计划",false,{"key":16,"text":17,"correct":18},"B","明确采购产品或服务的基本要求",true,{"key":20,"text":21,"correct":14},"C","进行市场调查，选择合格的产品供应单位",{"key":23,"text":24,"correct":14},"D","采用招标或协商等方式确定供应单位","采购管理应遵循下列程序： ( 1 ) 明确采购产品或服务的基本要求、采购分工及有关责任； ( 2 ) 进行采购策划，编制采购计划； ( 3 ) 进行市场调查，选择合格的产品供应或服务单位，建立名录； ( 4 ) 采用招标或协商等方式实施评审工作，确定供应或服务单位r ( 5 ) 签订采购合同； ( 6 ) 运输、验证、移交采购产品或服务； ( 7 ) 处置不合格产品或不符合要求的服务； ( 8 ) 采购资料归档。 @##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]