[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142608":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142608,799,2,"多选题","下列建设工程项目实施阶段策划的工作中，属于项目目标分析和再论证工作内容的有()（2013）",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","编制项目投资总体规划",true,{"key":16,"text":17,"correct":14},"B","编制项目建设总进度规划",{"key":19,"text":20,"correct":14},"C","项目功能分解",{"key":22,"text":23,"correct":14},"D","建筑面积分配",{"key":25,"text":26,"correct":27},"E","项目实施环境调查",false,"ABCD","项目目标的分析和再论证 其主要工作内容包括： ( 1 ) 投资目标的分解和论证； ( 2 ) 编制项目投资总体规划； ( 3 ) 进度目标的分解和论证； ( 4 ) 编制项目建设总进度规划； ( 5 ) 项目功能分解； ( 6 ) 建筑面积分配； ( 7 ) 确定项目质量目标。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]