[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142599":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1142599,799,1,"单选题","承包商就已完工，经检验合格的工程提出支付申请，监理工程师复核后，业主批准支付申请，此工作程序属于（ ）流程。 （2015）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","物资采购工作",false,{"key":16,"text":17,"correct":14},"B","信息处理工作",{"key":19,"text":20,"correct":14},"C","设计工作",{"key":22,"text":23,"correct":24},"D","管理工作",true,"工作流程组织包括： ( 1 ) 管理工作流程组织，如投资控制、进度控制、合同管理、付款和设计变更等流程； ( 2 ) 信息处理工作流程组织，如与生成月度进度报告有关的数据处理流程； ( 3 ) 物质流程组织，如钢结构深化设计工作流程，弱电工程物资采购工作流程，外立面施工工作流程等。 @##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]