[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142583":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142583,799,1,"单选题","施工单位编制项目管理任务分工表前，应完成的工作是（ ）。2017",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","明确各项管理工作的流程",false,{"key":16,"text":17,"correct":18},"B","详细分解项目实施各阶段的工作",true,{"key":20,"text":21,"correct":14},"C","落实各工作部门的具体人员",{"key":23,"text":24,"correct":14},"D","检查各项管理工作的执行情况","本题考查的是工作任务分工。施工单位编制项目管理任务分工表前，应结合项目的特点，对项目实施各阶段的费用(投资或成本）控制、进度控制、质量控制、合同管理、信息管理和组织与协调等管理任务进行详细分解。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]