[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142582":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142582,799,1,"单选题","下列组织工具图，表示的是( )。 （2012）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目结构图",true,{"key":16,"text":17,"correct":18},"B","工作流程图",false,{"key":20,"text":21,"correct":18},"C","组织结构图",{"key":23,"text":24,"correct":18},"D","合同结构图","项目结构图是一个组织工具，它通过树状图的方式对一个项目的结构进行逐层分解，以反映组成该项目的所有工作任务。项目结构图中，矩形表示工作任务（或第一层、第二层子项目等），矩形框之间的连接用连线表示。@##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]