[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142561":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142561,799,1,"单选题","（2019年真题）业主方项目管理的目标中，进度目标是指（）的时间目标。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目动用",true,{"key":16,"text":17,"correct":18},"B","竣工验收",false,{"key":20,"text":21,"correct":18},"C","联动试车",{"key":23,"text":24,"correct":18},"D","保修期结束","P5-8 业主方项目管理服务于业主的利益，其项目管理的目标包括项目的投资目标、进度目标和质量目标。其中投资目标指的是项目的总投资目标。进度目标指的是项目动用的时间目标，也即项目交付使用的时间目标，如工厂建成可以投人生产、道路建成可以通车、办公楼可以启用、旅馆可以开业的时间目标等。项目的质量目标不仅涉及施工的质量，还包括设计质量、材料质量、设备质量和影响项目运行或运营的环境质量等。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]