[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142558":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142558,799,2,"多选题","工程项目管理信息系统中，进度控制的功能有（ ）。2014",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","编制资源需求量计划",true,{"key":16,"text":17,"correct":18},"B","根据工程进展进行施工成本预测",false,{"key":20,"text":21,"correct":14},"C","进度计划执行情况的比较分析",{"key":23,"text":24,"correct":18},"D","项目估算的数据计算",{"key":26,"text":27,"correct":14},"E","确定关键工作和关键路线","ACE","本题考查的是进度控制的功能：计算工程网络计划的时间参数，并确定关键工作和关键路线；绘制网络图和计划横道图；编制资源需求量计划；进度计划执行情况的比较分析；根据工程的进展进行工程进度预测。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]