[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142555":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142555,799,2,"多选题","下列工程项目管理信息属于成本控制的功能有（ ）。 2016",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","投标估算的数据计算和分析",true,{"key":16,"text":17,"correct":14},"B","计划施工成本",{"key":19,"text":20,"correct":14},"C","计算实际成本",{"key":22,"text":23,"correct":14},"D","计划成本与实际成本的比较分析",{"key":25,"text":26,"correct":27},"E","设计概算",false,"ABCD","本题考查的是工程项目管理信息系统的功能。成本控制的功能包括：（1）投标估算的数据计算和分析；（2）计划施工成本；（3）计算实际成本；（4）计划成本与实际成本的比较分析；（5）根据工程的进展进行施工成本预测等。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]