[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142520":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142520,799,1,"单选题","项目结构信息编码的依据是（ ）。 2016",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目管理结构图",false,{"key":16,"text":17,"correct":18},"B","项目结构图",true,{"key":20,"text":21,"correct":14},"C","项目组织结构图",{"key":23,"text":24,"correct":14},"D","系统组织结构图","本题考查的是项目信息编码。项目的结构编码，依据项目结构图对项目结构的每一层的每一个组成部分进行编码。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]