[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142518":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142518,799,2,"多选题","为了满足建设工程项目施工成本管理的要求，项目成本项编码时应考虑的因素包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","投资估算",false,{"key":16,"text":17,"correct":18},"B","概预算",true,{"key":20,"text":21,"correct":18},"C","合同价",{"key":23,"text":24,"correct":18},"D","工程款支付",{"key":26,"text":27,"correct":14},"E","计价程序","BCD","本题主要考查项目成本项编码时应考虑因素。 BCD项：投资项编码（业主方）\u002F成本项编码（施工方）服务于投资控制工作\u002F成本控制工作。为了满足建设工程项目施工成本管理的要求，项目成本项编码时应考虑的因素包括概预算、投标估算、合同价、工程款支付等因素，服务于项目成本目标的动态控制。所以BCD项正确。 A项：投资估算属于业主编制投资项编码时考虑的因素，而非施工方编制的成本项编码时考虑因素。所以A项错误。 E项：计价程序不属于投资项编码和成本项编码时考虑的因素。所以E项错误。 综上所述，本题正确选项为BCD项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]