[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142509":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142509,799,1,"单选题","项目的进度项编码应综合考虑不同层次、不同深度和不同用途的进度计划工作项的需要，建立统一的编码，服务于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目进度目标的动态控制",true,{"key":16,"text":17,"correct":18},"B","项目进度计划的编制",false,{"key":20,"text":21,"correct":18},"C","项目管理控制",{"key":23,"text":24,"correct":18},"D","项目进度的确切实施","本题主要考查项目的进度项编码。 进度项编码服务于进度控制工作。建设项目的进度项编码应综合考虑不同层次、不同深度和不同用途的进度计划工作项的需要，建立统一的编码，服务于建设项目进度目标的动态控制。 综上所述，本题正确答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]