[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142470":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142470,799,1,"单选题","纠纷审议委员会的委员在建设工程项目开始时就介入项目，目的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","了解项目管理情况及其问题",true,{"key":16,"text":17,"correct":18},"B","预防纠纷发生",false,{"key":20,"text":21,"correct":18},"C","能够正确处理纠纷",{"key":23,"text":24,"correct":18},"D","保护当事人权益","本题主要考查国际建设工程承包合同争议的解决方式。 DRB的优点是DRB委员可以在项目开始时就介入项目，了解项目管理情况及其存在的问题，而且费用较低。 综上所述，本题正确答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]