[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142467":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142467,799,1,"单选题","关于FIDIC《EPC交钥匙项目合同条件》特点的说法，正确的是（ ）。( 2015真题 )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","适用于承包商作大部分设计的工程项目，承包商要按照业主的要求进行设计提供设备以及建造其他工程",false,{"key":16,"text":17,"correct":18},"B","合同采用固定总价合同，只有在特定风险出现时才调整价格",true,{"key":20,"text":21,"correct":14},"C","业主委派工程师管理合同，监督工程进度质量",{"key":23,"text":24,"correct":14},"D","承包商承担的风险较小","本题考查的国际常用的施工承包合同条件。承包商要负责所有的设计、采购和建造工作，合同计价采用固定总价，只有某些特定的风险才能调整价格。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]