[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142461":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142461,799,2,"多选题","FIDIC1999年出版的《施工合同条件》（新红皮书）主要用于（ ）的施工。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","由发包人设计的房屋建筑工程",true,{"key":16,"text":17,"correct":18},"B","由承包人设计的房屋建筑工程",false,{"key":20,"text":21,"correct":14},"C","由发包人设计的土木工程",{"key":23,"text":24,"correct":18},"D","由承包人设计的土木工程",{"key":26,"text":27,"correct":14},"E","由咨询工程师设计的土木工程","ACE","本题主要考查FIDIC系列合同条件。 FIDIC1999年出版的《施工合同条件》（新红皮书）主要用于由发包人设计的或由咨询工程师设计的房屋建筑工程和土木工程的施工项目。 综上所述，本题正确答案为ACE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]