[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142446":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1142446,799,1,"单选题","FIDIC合同条件和我国《建设工程施工合同示范文本》均规定，承包人必须在发出索赔意向通知后的（ ）天内或经过工程师同意的其他合理时间内向工程师提交一份详细的索赔文件和有关资料。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":14},"C","21",{"key":22,"text":23,"correct":24},"D","28",true,"*本题主要考查索赔程序。 根据FIDIC合同条件和我国《建设工程施工合同示范文本》规定，承包人必须在发出索赔意向通知后的28天内或经过工程师同意的其他合理时间内向工程师提交一份详细的索赔文件和有关资料。 综上所述，本题正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]