[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142444":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142444,799,1,"单选题","在工程实施过程中发生索赔事件以后，承包人首先应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","向工程师发出书面索赔意向通知",true,{"key":16,"text":17,"correct":18},"B","向建设主管部门报告",false,{"key":20,"text":21,"correct":18},"C","收集索赔证据并计算相应的经济和工期损失",{"key":23,"text":24,"correct":18},"D","向工程师递交正式索赔报告","本题主要考查的是索赔的方法和程序。 在工程实施过程中发生索赔事件以后或者承包人发现索赔机会，首先要提出索赔意向，即在合同规定的时间内将索赔意向用书面形式及时通知发包人或者工程师，向对方表明索赔愿望、要求或者声明保留索赔权利，这是索赔工作的第一步。 综上所述，正确选项为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]