[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142435":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1142435,799,1,"单选题","某工程的时标网络计划如下图，下列工期延误事件中，属于共同延误的是（ ）。 2016",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工作C因发包人原因和工作G因承包人原因各延误2周",false,{"key":16,"text":17,"correct":14},"B","工作D因发包人原因和工作F因承包人原因各延误2周",{"key":19,"text":20,"correct":21},"C","工作A因发包人原因和工作B因承包人原因各延误2周",true,{"key":23,"text":24,"correct":14},"D","工作E因发包人原因和工作F因承包人原因各延误2周","本题考查的是工期延误。当两个或两个以上的延误事件从发生到终止的时间完全相同时，这些事件引起的延误称为共同延误。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]