[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142433":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1142433,799,1,"单选题","可用于各种干扰事件和多种干扰事件共同作用所引起的工期索赔的计算方法是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","比例分析法",false,{"key":16,"text":17,"correct":14},"B","直接法",{"key":19,"text":20,"correct":21},"C","网络分析法",true,{"key":23,"text":24,"correct":14},"D","间接法","本题主要考查工期索赔。 工期索赔的计算方法： 可用于各种干扰事件和多种干扰事件共同作用所引起的工期索赔的计算方法是网络分析法。 综上所述，本题正确选项是C项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]