[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142431":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142431,799,1,"单选题","某工程项目总价值1000万元，合同工期为18个月，现承包人因建设条件发生变化需增加额外工程费用50万元，则承包方提出工期索赔为（ ）个月。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1.5",false,{"key":16,"text":17,"correct":18},"B","0.9",true,{"key":20,"text":21,"correct":14},"C","1.2",{"key":23,"text":24,"correct":14},"D","3.6","本题主要考查工期索赔的计算。 在实际工程中，若干扰事件仅影响某些单项工程、单位工程或分部分项工程的工期，要分析它们对总工期的影响，可采用较简单的比例类推法。 比例计算法的公式为：工期索赔值＝额外增加的工程量的价格\u002F 原合同总价×原合同总工期。 因此，本题中工期索赔值＝额外增加的工程量的价格\u002F 原合同总价×原合同总工期=50\u002F1000×18=0.9个月。 综上所述，本题正确选项为B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]