[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142430":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1142430,799,1,"单选题","由于承包商原因引起的延误一般是由于其管理不善所引起，比如计划不周密、组织不力、指挥不当等，但不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工组织不当，出现窝工或停工待料等现象",false,{"key":16,"text":17,"correct":14},"B","质量不符合合同要求而造成返工",{"key":19,"text":20,"correct":14},"C","资源配置不足",{"key":22,"text":23,"correct":24},"D","未能及时交付施工图样",true,"本题主要考查工期延误。 本题中未能及时交付施工图样属于因业主和工程师原因引起的延误，所以D项错误，D项当选。 本题为选非题，综上所述，本题正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]