[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142424":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1142424,799,1,"单选题","某基础工程合同价为2000万元，合同总工期为20个月，施工过程中因设计变更，导致增加额外工程400万元，业主同意工期顺延。则承包商按造价比例法可索赔工期（ ）个月。( 2015真题 )",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","8",false,{"key":16,"text":17,"correct":14},"B","6",{"key":19,"text":20,"correct":21},"C","4",true,{"key":23,"text":24,"correct":14},"D","2","本题考查的是索赔的计算。400÷（2000÷20）=4。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]