[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142421":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142421,799,1,"单选题","某国际工程合同额为5000万元人民币，合同实施天数为300天；由国内某承包商总承包施工，该承包商同期总合同额为5亿人民币，同期内公司的总管理费为1500万元；因为业主修改设计，承包商要求工期延期30天。该工程项目部在施工索赔中总部管理费的索赔额是（ ）万元。( 2015真题 )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","50",false,{"key":16,"text":17,"correct":18},"B","15",true,{"key":20,"text":21,"correct":14},"C","12",{"key":23,"text":24,"correct":14},"D","10","本题考查的是索赔费用的计算。该工程的总部管理费=1500×5000\u002F50000=150万，该工程可以索赔的总部管理费=30×150\u002F300=15万。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]