[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142413":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142413,799,2,"多选题","承包商可以向业主索赔利润的情况有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程范围变更",true,{"key":16,"text":17,"correct":14},"B","文件有缺陷",{"key":19,"text":20,"correct":21},"C","分部工程延期施工",false,{"key":23,"text":24,"correct":14},"D","文件技术性错误",{"key":26,"text":27,"correct":14},"E","业主未能提供现场","ABDE","本题主要考查费用索赔。 ABDE项：一般来说，由于工程范围的变更、文件有缺陷或技术性错误、业主未能提供现场等引起的索赔，承包商可以列入利润。所以ABDE项正确。 C项：对于工程暂停和延长工期的索赔，由于利润通常是包括在每项实施工程内容的价格之内的，而工程暂停或延长工期并未削减某些项目的实施，也未导致利润减少。所以，一般情况下，监理工程师不会同意在工程暂停或延长工期的费用索赔中加进利润损失。对于非承包商原因造成的工程暂停或延长工期的情况，可以申请工期索赔和费用索赔。所以C项错误。 综上所述，本题正确答案为ABDE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]