[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142406":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1142406,799,1,"单选题","建设工程索赔中，承包商计算索赔费用时最常用的方法是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","总费用法",false,{"key":16,"text":17,"correct":14},"B","修正的总费用法",{"key":19,"text":20,"correct":21},"C","实际费用法",true,{"key":23,"text":24,"correct":14},"D","修正的实际费用法","本题主要考查索赔费用的计算方法。 索赔费用的计算方法有：实际费用法、总费用法和修正的总费用法。 由上表可知，实际费用法是承包商计算索赔费用时最常用的方法。 综上所述，本题正确答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]