[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142402":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1142402,799,1,"单选题","（2020年真题）下列事件中，承包人不能提出工期索赔的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","开工前业主未能及时交付施工图纸",false,{"key":16,"text":17,"correct":14},"B","异营常恶劣的气候条件",{"key":19,"text":20,"correct":14},"C","业主未能及时支付工程款造成工期延误",{"key":22,"text":23,"correct":24},"D","因工期拖延，工程师指示承包人加快施工进度",true,"P322-327 工期索赔，一般指承包人向业主或者分包人向承包人要求延长工期。D选项工期拖延，属于承包人原因，不能索赔工期。 AC为业主原因，B为不可抗力。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]