[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142395":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142395,799,2,"多选题","某工程实行施工总承包模式，承包人将基础工程中的打桩工程分包给某专业分包单位施工，施工过程中发现地质情况与勘察报告不符而导致打桩施工工期拖延。在此情况下，（ ）可以提出索赔。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包人向发包人",true,{"key":16,"text":17,"correct":18},"B","承包人向勘察单位",false,{"key":20,"text":21,"correct":18},"C","分包人向发包人",{"key":23,"text":24,"correct":14},"D","分包人向承包人",{"key":26,"text":27,"correct":18},"E","发包人向监理","AD","本题主要考查承包商向业主的索赔。 施工的地质情况与勘查报告不符导致的索赔属于不可预见的外部障碍或条件索赔，承包人可以据此向发包人提出索赔； 施工工期拖延属于工期延期索赔，分包人可以据此向承包人提出索赔。 综上所述，本题正确答案为AD。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]