[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142381":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142381,799,1,"单选题","在施工期间，承包商可能遇到不能预见的地下岩石，导致工期拖延，这类风险应由（ ）承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",true,{"key":16,"text":17,"correct":18},"B","承包人",false,{"key":20,"text":21,"correct":18},"C","发包人和承包人共同",{"key":23,"text":24,"correct":18},"D","监理工程师","本题主要考查索赔的分类。 不可预见的外部障碍或条件索赔：如果在施工期间，承包人在现场遇到一个有经验的承包人通常不能预见到的外界障碍或条件，例如地质与预计的（发包人提供的资料）不同，出现未预见到的岩石、淤泥或地下水等，导致承包人损失，这类风险通常应该由发包人承担。 本题中的情况属于不可预见的外部障碍或条件索赔，因此其风险应由发包人承担。 综上所述，本题正确选项为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]