[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142374":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142374,799,1,"单选题","由于特殊恶劣气候，导致承包商工期延长和成本上升，则承包商有权索赔（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本，但不包括工期",false,{"key":16,"text":17,"correct":18},"B","工期，但不包括成本",true,{"key":20,"text":21,"correct":14},"C","工期、成本，但不包括利润",{"key":23,"text":24,"correct":14},"D","工期、成本和利润","本题主要考查工程索赔。 由于特殊恶劣气候，导致承包商工期延长和成本上升，属于不可抗力对工程的影响，对于不可抗力造成的费用损失由承包商和业主各自承担，不可抗力造成的工期延误，承包商可以将进行工期索赔。所以承包商有权索赔工期，但不能索赔成本。 综上所述，本题正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]