[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142372":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1142372,799,1,"单选题","关于工程变更的说法，正确的是（）。2018真题",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人可直接变更能缩短工期的施工方案",false,{"key":16,"text":17,"correct":18},"B","业主要求变更施工方案，承包人可以索赔相应费用",true,{"key":20,"text":21,"correct":14},"C","工程变更价款未确定之前，承包人可以不执行变更指示",{"key":23,"text":24,"correct":14},"D","因政府部门要求导致的设计修改，由业主和承包人共同承担责任","本题考查的是工程变更管理。选项A，承包商提出的工程变更，应该交予工程师审查并批准；选项C，即使工程变更价款没有确定，或者承包人对工程师答应给予付款的金额不满意，承包人也必须一边进行变更工作，一边根据合同寻求解决办法；选项D，由于业主要求、政府部门要求、环境变化、不可抗力、原设计错误等导致的设计修改，应该由业主承担责任。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]