[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142363":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1142363,799,1,"单选题","根据《建设工程施工合同（示范文本）》（GF-99-0201），不属于设计变更范围的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","更改工程有关的标高、基线、位置、尺寸",false,{"key":16,"text":17,"correct":14},"B","改变工程质量等级要求",{"key":19,"text":20,"correct":14},"C","增减合同中约定的工作量",{"key":22,"text":23,"correct":24},"D","改变工程施工的时间和顺序",true,"@##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]