[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142361":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142361,799,2,"多选题","根据工程实施的实际情况，可以提出工程变更的单位有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","承包方",true,{"key":16,"text":17,"correct":14},"B","业主方",{"key":19,"text":20,"correct":14},"C","设计方",{"key":22,"text":23,"correct":24},"D","供货商",false,{"key":26,"text":27,"correct":24},"E","质检站","ABC","本题主要考查的是工程变更管理中的工程变更程序。 根据工程实施的实际情况，可以提出工程变更的单位有：承包方、业主方、设计方。其余单位均无此权力。 综上所述，正确选项为ABC。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]