[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142358":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1142358,799,1,"单选题","工程师同意采用承包人的合理化建议，所发生费用和获得收益的分担或分享，由（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人决定",false,{"key":16,"text":17,"correct":14},"B","承包人决定",{"key":19,"text":20,"correct":21},"C","发包人和承包人另行约定",true,{"key":23,"text":24,"correct":14},"D","工程师决定","本题主要考查承包人要求的设计变更。 承包人在施工中提出的合理化建议被发包人采纳，若建议涉及到对设计图纸或施工组织设计的变更及对材料、设备的换用，则须经工程师同意。工程师同意采用承包人的合理化建议，所发生费用和获得收益的分担或分享，由发包人和承包人另行约定。 综上所述，本题正确选项是C项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]