[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142357":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1142357,799,1,"单选题","下列合同实施偏差的调整措施中，属于组织措施的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","增加人员投入",true,{"key":16,"text":17,"correct":18},"B","增加资金投入",false,{"key":20,"text":21,"correct":18},"C","变更技术方案",{"key":23,"text":24,"correct":18},"D","变更合同条款","本题考查的是合同实施偏差处理的的内容。 组织措施包括，增加人员投入，调整人员安排，调整工作流程和工作计划等。 A项：增加人员投入属于组织措施的内容，故当选。 B项：增加资金投入属于经济措施的内容，故不当选。 C项：变更技术方案属于技术措施的内容，故不当选。 D项：变更合同条款属于合同措施的内容，故不当选。 综上所述，本题正确选项为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]