[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142354":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1142354,799,1,"单选题","在施工合同实施中，“项目经理将各种任务的责任分解，并落实到具体人员”的活动属于（ ）的内容。2014",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","合同分析",false,{"key":16,"text":17,"correct":14},"B","合同跟踪",{"key":19,"text":20,"correct":21},"C","合同交底",true,{"key":23,"text":24,"correct":14},"D","合同实施控制","本题考查的是施工合同交底的任务。项目经理或合同管理人员应将各种任务或事件的责任分解，落实到具体的工作小组、人员或分包单位。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]