[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142344":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142344,799,2,"多选题","在施工合同分析中，发包人的合作责任有（ ）。( 2015真题 )",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工现场的管理，给发包人的管理人员提供生活和工作条件",false,{"key":16,"text":17,"correct":18},"B","及时提供设计资料、图纸、施工场地等",true,{"key":20,"text":21,"correct":18},"C","按合同规定及时支付工程款",{"key":23,"text":24,"correct":18},"D","对平行的各承包人和供应商之间的责任界限作出划分",{"key":26,"text":27,"correct":18},"E","及时作出承包人履行合同所必需的决策","BCDE","本题考查的是施工合同分析的任务。分析发包人（业主）的合作责任通常有如下几方面：（1）业主雇用工程师并委托其在授权范围内履行业主的部分合同责任；（2）业主和工程师有责任对平行的各承包人和供应商之间的责任界限作出划分，对这方面的争执作出裁决，对他们的工作进行协调，并承担管理和协调失误造成的损失；（3）及时作出承包人履行合同所必需的决策，如下达指令、履行各种批准手续、作出认可、答复请示，完成各种检査和验收手续等；（4）提供施工条件，如及时提供设计资料、图纸、施工场地、道路等；（5）按合同规定及时支付工程款，及时接收已完工程等。所以选BCDE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]