[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142332":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1142332,799,1,"单选题","在合同分析中，应明确工程变更的补偿范围，工程变更补偿范围通常以合同金额一定的百分比表示，百分比越大，则（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","合同金额越高",false,{"key":16,"text":17,"correct":14},"B","承包商利润越高",{"key":19,"text":20,"correct":21},"C","承包商的风险越大",true,{"key":23,"text":24,"correct":14},"D","对承包商的补偿越多","本题主要考查合同变更补偿范围。 工程变更的补偿范围，通常以合同金额一定的百分比表示。以材料价格上涨为例，若约定风险范围为10%，材料价格涨价10%即可调价；若约定风险范围为50%，那么涨价50%才可调价，价格在波动范围内不予补偿。所以这个百分比越大，则承包商的风险就越大。 综上所述，本题正确选项是C项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]