[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142255":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142255,799,2,"多选题","当建设工程施工承包合同的计价方式采用变动单价时，合同中可以约定合同单价调整的情况有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程量发生比较大的变化",true,{"key":16,"text":17,"correct":18},"B","承包商自身成本发生比较大的变化",false,{"key":20,"text":21,"correct":18},"C","业主资金不到位",{"key":23,"text":24,"correct":14},"D","通货膨胀达到一定水平",{"key":26,"text":27,"correct":14},"E","国家相关政策发生变化","ADE","本题考核的是单价合同的内容. 当采用变动单价合同时，合同双方可以约定一个估计的工程量，当实际工程量发生较大变化时可以对单价进行调整，同时还应该约定如何对单价进行调整； 当然也可以约定，当通货膨胀达到一定水平或者国家政策发生变化时，可以对哪些工程内容的单价进行调整以及如何调整等。因此，承包商的风险就相对较小。承包商自身成本较大变化和业主资金不到位不属于调整单价的理由。 综上所述，正确选项为ADE。*",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]