[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142253":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1142253,799,1,"单选题","采用单价合同时，最后工程结算的总价是根据（ ）计算确定的。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发包人提供的清单工程量及承包方所填报的单价",false,{"key":16,"text":17,"correct":14},"B","发包人提供的清单工程量及承包方实际发生的单价",{"key":19,"text":20,"correct":14},"C","实际完成并经工程师计量的工程量及承包人实际发生的单价",{"key":22,"text":23,"correct":24},"D","实际完成并经工程师计量的工程量及承包人所填报的单价",true,"本题考核的是单价合同的概念。 采用单价合同时，最后工程结算的总价是根据实际完成并经工程师计量的工程量及承包人所填报的单价计算确定的。 综上所述，正确选项为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]