[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142250":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1142250,799,1,"单选题","对于采用单价合同招标的工程，如投标书中有明显的数字计算错误，业主有权先做出修改再评标。当总价和单价的计算结果不一致时，正确的做法（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","按市场价调整单价",false,{"key":16,"text":17,"correct":14},"B","分别调整单价和总价",{"key":19,"text":20,"correct":14},"C","以总价为准调整单价",{"key":22,"text":23,"correct":24},"D","以单价为准调整总价",true,"本题考查的是单价合同运用的内容。 单价合同的特点就是单价优先。虽然在投标报价、评标以及签订合同中，人们常常注重总价格，但在工程款结算中单价优先，对于投标书中有明显的数字计算错误，业主有权先做出修改再评标。当总价和单价的计算结果不一致时，以单价为准调整总价。 综上所述，本题正确选项为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]