[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142248":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142248,799,2,"多选题","对建设周期一年半以上的工程项目，采用变动总价合同时，应考虑引起价格变化的因素有（ ）。2014",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","银行利率的调整",false,{"key":16,"text":17,"correct":18},"B","材料费的上涨",true,{"key":20,"text":21,"correct":18},"C","人工工资的上涨",{"key":23,"text":24,"correct":18},"D","国家政策改变引起的工程费用上涨",{"key":26,"text":27,"correct":14},"E","设计变更引起的费用变化","BCD","本题考查的是对建设周期一年半以上的工程项目，则应考虑下列因素引起的价格变化问题：劳务工资以及材料费用的上涨；其他影响工程造价的因素，如运输费、燃料费、电力等价格的变化；外汇汇率的不稳定；国家或者省、市立法的改变引起的工程费用的上涨。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]