[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142245":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142245,799,2,"多选题","采用固定总价合同时，承包商承担的价格风险有（）。2018真题",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","漏报项目",true,{"key":16,"text":17,"correct":18},"B","工程范围不确定",false,{"key":20,"text":21,"correct":14},"C","报价计算错误",{"key":23,"text":24,"correct":14},"D","物价和人工费上涨",{"key":26,"text":27,"correct":18},"E","工程量计算错误","ACD","本题考查的是总价合同。价格风险有报价计算错误、漏报项目、物价和人工费上涨等；工作量风险有工程量计算错误、工程范围不确定、工程变更或者由于设计深度不够所造成的误差等。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]