[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142242":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1142242,799,2,"多选题","按照我国相关规定，变动总价合同可以调整总价的情况包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","通货膨胀",true,{"key":16,"text":17,"correct":14},"B","设计变更",{"key":19,"text":20,"correct":21},"C","承包商施工成本增加",false,{"key":23,"text":24,"correct":14},"D","工程量变化",{"key":26,"text":27,"correct":21},"E","一周内停电时间超过6小时","ABD","本题主要考查变动总价合同的特点。 变动总价合同的合同价格是以图纸及规定、规范为基础，按照时价进行计算，得到包括全部工程任务和内容的暂定合同价格。它是一种相对固定的价格，在合同执行过程中，由于通货膨胀等原因而使所使用的工、料成本增加时，可以按照合同约定对合同总价进行相应的调整。一般由于设计变更、工程量变化和其他工程条件变化所引起的费用变化也可以进行调整。 综上所述，本题正确选项为ABD项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]