[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1142241":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1142241,799,1,"单选题","一般而言，采用固定总价合同时，承包商的投标报价较高的原因是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","承包商丧失了今后一切的索赔权力",false,{"key":16,"text":17,"correct":14},"B","业主因今后工程款结算的工作量减少而给予承包商的费用补偿",{"key":19,"text":20,"correct":14},"C","业主今后可以增加工程范围和内容而不给予承包商另外的费用补偿",{"key":22,"text":23,"correct":24},"D","承包商会将工程量及一切不可预见因素的风险补偿加到投标报价之中",true,"本题考核的是工程合同的类型及特点。 固定总价合同的价格计算是以图纸及规定、规范为基础，工程任务和内容明确，业主的要求和条件清楚，合同总价一次包死，固定不变，即不再因为环境的变化和工程量的增减而变化。在这类合同中，承包商承担了全部的工作量和价格的风险。因此，承包商在报价时应对一切费用的价格变动因素以及不可预见因素都做充分的估计，并将其包含在合同价格之中。 综上所述，正确选项为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]